Bismarck WWTF – Trickling Filter Improvements

Bid Date: July 2015

Final Contract: $16.5million

Contract Completion: July 2017
Actual Completion: July 2017
Owner: City of Bismarck, ND

Engineer: AE2S

Project Details

This hard-bid project included construction of a new trickling filter pump station, trickling filter, site improvements throughout. PKG’s successful relationship with the City and AE2S led to an additional award for the second phase of the project.